Construction updates: Linden Avenue North undergoes redevelopment; UW Pedestrian/Bike Bridge construction

Image

Linden Avenue North six-month closure between N 130th & N 135th streets

Starting Wednesday, Sept. 5, Seattle Department of Transportation (SDOT) contractor crews will be closing Linden Avenue N to southbound traffic as they redevelop Linden Avenue North into a neighborhood-friendly roadway. 

Image

      - What's happening now?
Linden Avenue N will be closed to southbound traffic between N 130th and N 135th streets starting for approximately six months. This closure extends the southbound closure currently in place from N 135th to N 145th streets. Crews will install a new storm drainage system and construct new roadway, curbs, gutters and sidewalks.

     - Linden Avenue N between N 128th and N 130th streets remains closed to all traffic
Crews continue installation of the storm drainage system in the center roadway, construction of sidewalks and grinding, paving and landscaping. The closure will continue until late September/early October, followed by one lane of northbound travel through mid-November to complete sidewalks and landscaping.

     - Construction, southbound detours continue between N 135th and N 145th streets SDOT crews will continue working at the north end of the project area, between N 135th and N 145th streets, to complete paving, construction of sidewalks, curbs and bioswales. Southbound traffic will remain detoured.

The stretch of roadway between N 135th and N 141th streets will reopen to southbound traffic when crews are not working in the area.

Visit the project website for more information.

 

UW Pedestrian/Bike Bridge construction: 

Image

Current construction at the UW Station along Montlake Blvd. Courtesy of Sound Transit

Construction of the University of Washington Ped/Bike Bridge continues throughout the month of September. Impacts for the month of September:

The weekend of Sept. 7 & 8

- From Friday Sept. 7 at 11 p.m. to Saturday Sept. 8 at 8 p.m.
- Closing the Metro SB lane between NE Pacific Place and Street

The weekend of Sept. 14 through 16 

- From Friday Sept. 14 at 7 p.m. to Sunday Sept. 16 at 6 p.m.
- Restripe Montlake Blvd.
- Cutting out curb, install footing in prep for bridge work
- Close all NB lanes on Montlake and sidewalk between NE Pacific Place and Pacific  Street
- Close 1 SB lane

The weekend of Sept. 22

- From Saturday, Sept. 22 at 5 a.m. to Saturday, Sept. 22 at 4 p.m.
- Closing the SB Metro bus lane
- Closing NB lane on Montlake Blvd and sidewalk between NE Pacific Place and Pacific  Street

The weekend of Sept. 28 through Oct. 1

- Friday, Sept. 28 at  7 p.m. to Saturday, Sept. 29 at 4 a.m.
- Close all NB lanes on Montlake and sidewalk between NE Pacific Place and Pacific  Street
- Close 1 SB lane
- Saturday, Sept. 29 at 4 a.m. to Monday, Oct. 1 at 5 a.m.
- Full closure of all lanes between NE Pacific Place and Pacific  Street